12 chapters + 3 appendices. Click any TOC entry below to jump. Members First - G$D - True North.
1. Exam Overview & Test-Day Strategy
1.1 What this credential is
The CSA ASCR4 Sprinkler Business Certificate Holder credential is the qualification track recognized in Phoenix and many other AHJs as a 'competent party' for fire sprinkler system work under PFC sec 105.8. It belongs to a family of CSA Level 4 credentials, each tied to a specific scope (sprinkler, fire alarm, special hazards, etc.). For sprinkler contractors, the ASCR4 is the credential that lets the company hold a Business Certificate to install, service, repair, and inspect water-based fire protection systems.
| Item |
Detail |
| Fee |
$250 per attempt |
| Passing score |
80% |
| Format |
Computer-based, open-book, proctored |
| Recertification |
Re-take every 3 years |
| Reference editions allowed |
NFPA 13 / 13D / 13R 2022 or 2025; NFPA 14 2024; NFPA 20 2022 or 2025; NFPA 25 2023; IBC 2021 or 2024; CSA Study Guide 2025 |
| Books rules |
Publisher-bound only, permanent tabs OK, no Post-Its, no loose pages, highlighting OK before exam |
| Calculators |
Non-programmable scientific calculator allowed |
| Time |
Typically 3 hours |
1.3 Open-book strategy
'Open-book' is a trap for the unprepared. The exam is timed and the codes are dense. Candidates who fail typically do so because they spend too much time hunting for answers in books they haven't pre-tabbed. The ones who pass walk in with their books already organized and know within seconds where to find each topic.
Pre-tab targets
- NFPA 13 - Chapter 10 (sprinkler position), Chapter 19 (design approaches), Chapter 27 (hydraulics), Chapter 29 (acceptance testing)
- NFPA 13 - Tables for protection area, hose stream allowance, density-area curves
- NFPA 13D and 13R - water duration, design sprinkler counts, omitted areas
- NFPA 14 - hose connection class table, pressure limits, hydrostatic test
- NFPA 20 - performance points, fuel sizing, pump room, jockey pump rules
- NFPA 25 - frequency tables (most-tested area in ITM)
- IBC sec 903.2 sprinkler trigger thresholds for each occupancy
- OSHA 1910.147 LOTO 6-step procedure, 1926.501 fall trigger, 1926.652 trench depth
Reading questions correctly
CSA exam stems often hinge on small wording. Always read each question twice before reaching for a book. Watch for these words:
| Trigger word |
What it means |
Common trap |
| EXCEPT |
All choices are true except one - find the false one |
Reading too fast and picking the first true statement |
| NOT |
Same as EXCEPT - find the wrong choice |
Glossing over the negative |
| MOST or BEST |
There is a best answer even if multiple are technically correct |
Picking the first acceptable answer |
| MINIMUM or MAXIMUM |
The number is the floor or ceiling, not the typical |
Confusing 'at least' with 'no more than' |
| All of the following |
Watch for outliers - one option doesn't fit |
Picking what's most familiar |
Time management
Most ASCR4 exams give about 3 hours for 80 questions. That averages 2 minutes 15 seconds per question. Use a two-pass strategy: first pass through the entire exam answering only what you know cold (skip anything that needs a book lookup); flag the rest. Second pass uses your books for the flagged questions. Third pass reviews flagged questions and your initial answers.
1.4 What this guide covers
Each subject in this guide is structured the same way: an Overview that frames the standard's purpose, a Key Definitions section, a detailed Rules section organized as look-up tables with section citations, Common Pitfalls that traps the most candidates, a Tab-the-Book guide, and a Practice Strategy. The end has Appendices with quick-reference cards, conversion charts, and a Phoenix AHJ section.
Use this guide alongside the Practice Quiz and Flashcards modes. Read the chapter, drill the matching subject, then come back and review the Common Pitfalls section.
2. NFPA 13 - Standard for the Installation of Sprinkler Systems
This is the single most heavily-weighted subject on the ASCR4. The CSA exam treats NFPA 13 as the foundation of the entire trade, and roughly one out of every four to five questions on a typical exam comes from this standard. Master Chapter 10 (sprinkler position), Chapter 19 (design approaches), and Chapter 29 (acceptance testing) and you build the floor that everything else stands on.
2.1 Scope and applicability
NFPA 13 applies to commercial, industrial, institutional, mercantile, storage, and high-rise residential sprinkler systems. It does NOT apply to single- and two-family dwellings (use NFPA 13D), residential occupancies up to four stories (NFPA 13R), or fire pumps as installed equipment (NFPA 20). Standpipes are NFPA 14 territory.
The 2022 edition consolidated several earlier NFPA standards into one document. The 2025 edition makes additional minor revisions. The CSA accepts either edition for the open-book exam.
2.2 Key definitions
| Term |
Definition |
| Standard spray sprinkler |
A spray sprinkler with a deflector designed to throw water in an approximately hemispherical pattern. |
| Quick-response (QR) sprinkler |
A sprinkler with a thermal element that responds significantly faster than standard-response. Permits design area reduction up to 40 percent in light and ordinary hazard. |
| Extended-coverage (EC) sprinkler |
A sprinkler with a larger protection area than standard. Subject to the 4x obstruction rule rather than 3x. |
| ESFR (Early Suppression Fast Response) |
Designed to suppress (not just control) high-challenge storage fires. Requires 36 in. clearance from deflector to top of storage. |
| Coverage area |
The maximum floor area protected by a single sprinkler, set by the protection area table in Chapter 10 based on hazard and construction type. |
| Hazard classification |
The fire-risk category that drives density, area, and hose stream demand: Light, Ordinary 1 and 2, Extra 1 and 2, and storage classifications. |
| Density-area method |
Hydraulic design method where you select a density (gpm per sq ft) and a design area (sq ft of operating sprinklers) from a curve in Chapter 19. |
| K-factor |
Sprinkler discharge coefficient. Q = K times square root of P. K-5.6 is the most common floor for NFPA 13 commercial. |
2.3 Sprinkler position - Chapter 10
Chapter 10 governs where a sprinkler is allowed to sit relative to the ceiling, walls, other sprinklers, obstructions, and storage or floor below.
Deflector distance below ceiling
| Sprinkler type / construction |
Deflector below ceiling |
Section |
| Standard spray pendent or upright, unobstructed |
1 in. minimum to 12 in. maximum |
10.2.6.2.1 |
| Standard spray, obstructed combustible (e.g., wood joist) |
1 in. minimum to 6 in. maximum |
10.2.6.2.2 |
| Standard spray, obstructed noncombustible (e.g., bar joist) |
1 in. minimum to 12 in. maximum |
10.2.6.2.3 |
| Sidewall spray |
4 in. to 6 in. below ceiling |
10.3.6 |
| Concealed pendent (cover plate) |
Per listing - typically flush |
10.2.6.2.6 |
Tab tip: The 1-12 rule for unobstructed pendent or upright is the single most-tested number in NFPA 13. Drill it.
Spacing between sprinklers and from walls
| Hazard / construction |
Max spacing on center |
Max coverage area |
Max distance from wall |
| Light Hazard - hydraulic, unobstructed |
15 ft |
225 sq ft |
7 ft 6 in. |
| Light Hazard - hydraulic, obstructed combustible |
15 ft |
200 sq ft |
7 ft 6 in. |
| Light Hazard - Small Room Rule |
15 ft |
225 sq ft |
9 ft (special) |
| Ordinary Hazard - hydraulic |
15 ft |
130 sq ft |
7 ft 6 in. |
| Extra Hazard, density >= 0.25 gpm/sq ft |
12 ft |
100 sq ft |
6 ft |
Minimum distance between two standard spray sprinklers (without baffling) is 6 ft on center. Less than 6 ft requires a baffle 8 in. long by 6 in. high between them, with the top 2 to 3 in. above the deflectors. Reason: cold soldering. Without a baffle, water from one sprinkler cools the bulb of the next and prevents it from operating.
The Small Room Rule
Sec 10.2.5.2.3.1 allows a single sprinkler up to 9 ft from a wall in a small space. ALL of these must be true:
- Light hazard occupancy
- Room not exceeding 800 sq ft
- Walls and ceiling are noncombustible or limited-combustible
- Construction is unobstructed
Common test trap: candidates assume the rule applies whenever the room is 'small.' The 800 sq ft and noncombustible walls requirements are the gates - if either fails, the standard 7 ft 6 in. wall distance applies.
Obstructions and the 3x Rule
Sec 10.2.7: a standard spray sprinkler shall be located at least three times the maximum dimension of the obstruction away from it, with a maximum required distance of 24 in. For extended-coverage sprinklers, the rule becomes 4x with a 36 in. cap.
Worked example: a 6 in. wide duct under a standard spray sprinkler. 3 x 6 in. = 18 in. Sprinkler must be at least 18 in. from the duct horizontally. If the duct were 10 in. wide, the calculation would give 30 in. but the rule caps at 24 in.
Storage clearance below deflector
| Sprinkler type |
Clearance to top of storage |
Section |
| Standard spray |
18 in. minimum |
10.2.6.4 |
| ESFR / CMSA / large-drop |
36 in. minimum |
23.2 |
| In-rack (within rack levels) |
Per listing - typically 6 in. |
Storage chapters |
2.4 Hazard classification - Chapter 4 + Annex
Hazard classification drives density, design area, hose stream allowance, and water duration. Misclassify and your entire hydraulic design is wrong.
| Class |
Typical occupancies |
| Light Hazard |
Offices, churches, schools, hospitals, libraries (small stack), museums, theaters (no stage) |
| Ordinary Hazard 1 |
Parking garages, electronics plants, bakeries, dairies, laundries, restaurants |
| Ordinary Hazard 2 |
Woodworking shops, dry cleaners, repair garages, large libraries (book stack), printing/publishing, post offices, machine shops, stages |
| Extra Hazard 1 |
Aircraft hangars, die casting, plywood/particleboard, sawmills, upholstering with plastic foam, rubber reclaiming |
| Extra Hazard 2 |
Asphalt saturating, flammable liquid spraying, plastics processing, fluid spreading, varnish/paint dipping, solvent cleaning |
2.5 Density and area - Chapter 19
The density-area family is the spine of hydraulic design. Memorize this matrix:
| Hazard |
Density (gpm/sq ft) |
Design area (sq ft) |
Hose stream (gpm) |
Duration (min) |
| Light Hazard |
0.10 |
1500 |
100 |
30 |
| Ordinary Hazard 1 |
0.15 |
1500 |
250 |
60-90 |
| Ordinary Hazard 2 |
0.20 |
1500 |
250 |
60-90 |
| Extra Hazard 1 |
0.30 |
2500 |
500 |
90 |
| Extra Hazard 2 |
0.40 |
2500 |
500 |
120 |
Design area adjustments - sec 19.3.3.2
- Dry-pipe systems: design area increased by 30 percent (water-delivery delay)
- Sloped ceilings exceeding 1 in 6 (16.7 percent): design area increased by 30 percent
- Quick-response sprinklers in light or ordinary hazard: design area reduced by up to 40 percent (never below 1500 sq ft)
- High-temperature sprinklers in extra hazard occupancies: design area reduced by 25 percent
2.6 Acceptance testing - Chapter 29
| Test |
Pressure |
Duration |
Acceptance criteria |
Section |
| Aboveground hydrostatic |
200 psi (or 50 psi above max working if working > 150 psi) |
2 hours |
No leakage |
29.2.1.1 |
| Dry/preaction air leak |
40 psi |
24 hours |
Maximum 1.5 psi loss |
29.2.2 |
| Underground hydrostatic |
200 psi (per NFPA 24) |
2 hours |
Permissible leakage by formula |
NFPA 24 sec 10.10.2.2 |
| FDC piping (existing system, every 5 yr per NFPA 25) |
150 psi |
2 hours |
No leakage |
NFPA 25 sec 13.7.4 |
On a new system, FDC piping is hydrostatically tested at the same pressure as the system per NFPA 13. Only the periodic re-test under NFPA 25 uses 150 psi for 2 hours.
2.7 Hangers and bracing - Chapters 17 and 18
Hanger spacing for steel pipe
| Pipe size |
Maximum hanger spacing |
| 1 in. |
12 ft |
| 1.25 in. |
12 ft |
| 1.5 in. |
15 ft |
| 2 in. and larger |
15 ft |
Branch line hangers shall be installed within 12 in. of each upright sprinkler. Hangers must also be installed within 6 ft of the end of any branch line.
Sway bracing for seismic protection
| Brace type |
Maximum spacing |
Notes |
| Lateral sway brace on cross main |
40 ft on center |
Last brace within 6 ft of end of pipe |
| Longitudinal sway brace on cross main |
80 ft on center |
Resists piping movement along its length |
| Flexible coupling on riser |
Within 24 in. above and below floor penetrations |
Absorbs differential building movement |
| 4-way brace |
Required at top of riser and at last sprinkler on long branch lines |
Per Ch. 18 details |
Note: Earthquake protection (sec 18.1) is required where the AHJ or building code triggers it - typically based on the building's Seismic Design Category. The IBC drives this, not NFPA 13.
2.8 System components - Chapter 16
Pressure gauges - required locations
- System main drain
- Both sides of every riser check valve
- Both sides of every alarm check valve
- Both sides of every PRV
- Floor control valve drain on multi-floor systems
Inspector's test connection (ITC)
Per sec 16.14 the ITC shall be at least 1 in. nominal pipe size, equipped with a sight glass and an orifice equivalent to the smallest sprinkler in the system, and discharge to a drain or atmosphere outside the building.
Fire department connection (FDC)
- Two 2.5 in. female connections (or single Storz where listed/AHJ-approved)
- FDC piping at least 4 in. nominal for systems requiring 350 gpm or more
- Located within 100 ft of an approved fire hydrant
- Identified with a sign indicating the systems served
2.9 Common pitfalls
Mistake 1: Confusing 1-12 (unobstructed) with 1-6 (obstructed combustible).
Both come from sec 10.2.6.2. Read the construction type in the stem: wood-joist with combustible concealed = 1-6. Open ceiling or concrete deck = 1-12.
Mistake 2: Adding hose stream allowance at the wrong location.
Hose stream is added at the connection to the water supply (base of system riser or city main), NOT at the most-remote sprinkler.
Mistake 3: Forgetting the design area increase for dry pipe.
If the system is dry pipe, your design area goes up by 30 percent.
Mistake 4: Misreading the 3x rule maximum.
Calculate 3x the obstruction width; if your answer exceeds 24 in., use 24 in. instead.
2.10 Tab the book - NFPA 13
- Chapter 4 - General Requirements (single fire area limits)
- Chapter 8 - Sprinklers (min 7 psi, max 175 psi, K-factors)
- Chapter 10 - Sprinkler Position (THE chapter to know)
- Chapter 16 - System Components (gauges, ITC, FDC)
- Chapter 17 - Hanging (hanger spacing tables)
- Chapter 18 - Bracing and Restraint (sway brace spacing)
- Chapter 19 - Design Approaches (density-area family)
- Chapter 23 - ESFR Sprinklers (storage)
- Chapter 27 - Plans and Calculations (hydraulics)
- Chapter 29 - System Acceptance (tests)
3. NFPA 13D and 13R - Residential Sprinkler Systems
These two standards split the residential world. NFPA 13D covers one- and two-family dwellings, manufactured homes, and townhouses (added 2022). NFPA 13R covers residential occupancies up to four stories above grade plane and 60 ft in height. Above that, full NFPA 13 takes over.
3.1 NFPA 13D - One- and Two-Family Dwellings
Purpose - this drives every other rule
NFPA 13D's stated purpose (sec 1.2) is life safety in the room of fire origin. It is NOT property protection. The standard is engineered to give occupants enough time to escape before flashover, not to save the structure or its contents.
If you are unsure on a 13D stem, ask: does this rule make sense if the only goal is getting people out alive? If yes, it is probably the right answer.
Scope and water supply
| Topic |
Requirement |
Section |
| Scope (2022) |
1- and 2-family dwellings, manufactured homes, townhouses |
1.1 |
| Water duration - standard |
10 minutes |
6.1.2 |
| Water duration - one-story under 2,000 sq ft |
7 minutes |
6.1.2 |
| Max design sprinklers (flat smooth ceiling) |
2 sprinklers (or all in compartment if fewer) |
8.1.2 |
| Pipe materials permitted |
Steel, copper, CPVC, PEX (all listed for fire sprinkler service) |
7.3 |
| Multipurpose plumbing+sprinkler systems |
Permitted - unique to 13D |
Ch. 7 |
| Antifreeze (after 9/30/2022) |
UL 2901 listed only |
Ch. 8 |
Omitted areas - 13D
- Bathrooms with floor area not exceeding 55 sq ft
- Closets with floor area not exceeding 24 sq ft and least dimension not exceeding 3 ft
- Garages, carports, and open attached porches
- Attics not used for living or storage
- Concealed spaces with no access
3.2 NFPA 13R - Residential up to 4 Stories
Scope and limits
NFPA 13R's scope is residential occupancies up to and including four stories above grade plane in buildings not exceeding 60 ft above grade plane. Both limits must be true.
| Topic |
Requirement |
Section |
| Scope - height |
4 stories above grade plane AND <= 60 ft above grade plane |
1.1; IBC 903.3.1.2 |
| Water duration |
30 minutes |
6.1 |
| Max design sprinklers |
Up to 4 quick-response residential |
6.4 |
| Sprinklers in dwelling units |
Quick-response residential, listed for residential occupancy |
6.7 |
| Egress corridors |
SPRINKLERS REQUIRED - cannot be omitted |
6.6 |
| Water flow alarm |
Required |
10.2 |
Omitted areas - 13R
Bathrooms <= 55 sq ft, closets <= 24 sq ft (least dim <= 3 ft), attics not used for living/storage, garages and carports, open balconies. Public corridors that are part of the means of egress are NOT eligible for omission.
3.3 13D vs 13R - quick comparison
| Topic |
NFPA 13D |
NFPA 13R |
| Scope |
1-2 family, manufactured, townhouses |
Residential up to 4 stories AND 60 ft |
| Purpose |
Life safety, room of fire origin |
Life and modest property |
| Water duration |
10 min (7 if one-story under 2,000 sq ft) |
30 min |
| Max design sprinklers |
2 |
Up to 4 |
| Multipurpose system |
Permitted |
Not addressed (use NFPA 13) |
| Egress corridors |
Not applicable to single-family layout |
REQUIRED to be sprinklered |
| Pipe materials |
Steel, copper, CPVC, PEX |
Steel, copper, CPVC, PEX |
3.4 Common pitfalls
Mistake 1: Confusing the design sprinkler counts.
13D = 2 sprinklers max. 13R = up to 4 sprinklers.
Mistake 2: Forgetting the 60 ft AND 4-story limit on 13R.
Both must be true. A 4-story building taller than 60 ft requires full NFPA 13.
Mistake 3: Assuming corridors can be omitted under 13R.
They cannot. Corridors that serve as means of egress are always sprinklered under 13R.
4. NFPA 14 - Standpipe and Hose Systems
NFPA 14 governs the piping system that delivers water from a fire department connection or building water supply to hose connections distributed throughout a building. The 2024 edition is the current reference and brought one significant change: all dry-type standpipes must now be air-supervised at 7 to 20 psi.
4.1 Class definitions
| Class |
Outlet size |
Min residual pressure |
Min flow |
Audience |
| I |
2.5 in. |
100 psi at remote outlet |
500 gpm + 250 each additional (cap 1000 sprinklered, 1250 not) |
Fire department only |
| II |
1.5 in. |
65 psi at remote outlet |
100 gpm fixed |
Trained occupants / first response |
| III |
Both 1.5 and 2.5 |
100 / 65 psi |
Same as Class I |
Both audiences |
4.2 Pressure limits and PRVs
Sec 7.2.3 caps maximum static pressure at any individual hose connection at 175 psi. Above 175 psi static, a pressure-reducing valve (PRV) is required. For 1.5 in. hose stations, residual pressure is also capped at 100 psi during flow.
Why 175 psi static? Above that, a firefighter opening a valve loses control of the hose due to reaction force. PRVs aren't paperwork - they're firefighter safety.
4.3 Hose connection locations - sec 7.3
- Each main floor landing of every required interior exit stairway
- Each side of horizontal exit walls (between fire areas)
- In exit passageways at the entrance to the building
- At the highest landing of stairways with stair access to the roof
Hose connection height: 3 ft to 5 ft above the floor.
4.4 Flow demand sizing - sec 7.10
- 500 gpm at the most-remote standpipe (this is two 2.5 in. outlets at one location)
- 250 gpm for each additional standpipe in the building
- Cap at 1000 gpm for fully sprinklered buildings, 1250 gpm for non-sprinklered
Class II is fixed at 100 gpm regardless of how many hose stations exist.
Worked example: a 3-standpipe sprinklered building. 500 gpm + 250 + 250 = 1000 gpm. That hits the cap exactly.
4.5 Travel distance - sec 7.3.2
- 200 ft in fully sprinklered buildings
- 150 ft in non-sprinklered buildings
4.6 Hydrostatic and acceptance testing
New standpipe systems are hydrostatically tested at 200 psi for 2 hours. NFPA 25 Ch. 6 governs periodic re-test of manual and semi-automatic dry standpipes - 200/2 every 5 years.
4.7 Common pitfalls
Mistake 1: Misreading 'most remote' as 'farthest from FDC.'
'Hydraulically most remote' means lowest residual pressure at design flow - typically the highest connection in a high-rise.
Mistake 2: Forgetting the 175 psi static cap.
When a question asks 'what triggers a PRV requirement,' the answer is static pressure above 175 psi at the connection.
5. NFPA 20 - Stationary Pumps for Fire Protection
Fire pumps are the second-heaviest weighted subject after NFPA 13. The 2022 and 2025 editions are both acceptable references.
- 100% of rated flow at 100% of rated pressure (the design point)
- 150% of rated flow at not less than 65% of rated pressure (the overload point)
- Churn (shutoff, no flow) shall not exceed 140% of rated pressure
Memorize: 100/100, 150/65, churn <=140. This shows up on the ASCR4 every single time.
5.2 Pump types and applications
| Pump type |
Typical use |
Suction lift? |
| Horizontal split-case |
Most common large-capacity pump for buildings |
No - positive suction head required |
| End suction |
Mid-size buildings, simpler than split-case |
No |
| Vertical in-line |
Compact installations with limited floor space |
No |
| Vertical turbine |
Open water sources, below-grade tanks, suction lift |
YES - the only listed type |
| Positive displacement |
Foam systems, water-mist |
Limited |
Vertical turbine is the only pump type listed by NFPA 20 for suction-lift conditions.
5.3 Pump room requirements
| Topic |
Requirement |
Section |
| Min ambient temperature |
40 deg F |
4.14 |
| Separation - high-rise |
2-hour fire-rated |
4.12 |
| Separation - non-high-rise NFPA 13 throughout |
1-hour fire-rated |
4.12 |
| Separation - outdoor pump house |
50 ft from other buildings |
4.12 |
| Drainage |
Floor drain or sump for water leakage |
4.14 |
5.4 Suction and discharge piping
| Item |
Limit |
Section |
| Suction pipe velocity at 150% rated flow |
<= 15 ft/sec |
4.16 |
| Discharge pipe velocity at 150% rated flow |
<= 20 ft/sec |
4.16 |
| Eccentric reducer at suction |
Flat side UP (prevents air pockets) |
4.16.7 |
| Reducer at discharge |
Concentric |
4.16 |
5.5 Jockey pump - sec 4.27
- Capacity: make up the allowable system leakage rate in 10 minutes
- Minimum capacity: 1 gpm even if calculated leakage is lower
- MUST be smaller than the smallest single-sprinkler discharge
Pressure setpoint cascade
- Jockey stop pressure = pump churn + city static pressure
- Jockey start = jockey stop minus 10 psi
- Main fire pump start = jockey start minus 5 psi
- Each additional pump start: 10 psi below the previous pump
5.6 Diesel-driven pumps
| Topic |
Requirement |
Section |
| Fuel tank capacity |
1 gal/HP + 5% expansion + 5% sump (~8 hr run) |
11.4 |
| Battery configuration |
Two batteries, each independently capable of starting |
11.2.5 |
| Cranking cycles |
6 cycles, 15 sec on / 15 sec off, alternating batteries |
12.4 |
| Cooling |
Heat exchanger or radiator listed for the engine |
11.2 |
| Fuel level when in service |
Maintained at no less than 2/3 capacity |
NFPA 25 sec 8.3.4 |
5.7 Electric pumps
- Two utility sources OR utility + on-site generator with listed transfer switch
- Conductor sizing at least 125% of motor full-load current
- Disconnecting means rated for locked-rotor current; lockable in CLOSED position
- Voltage drop during start <= 15% from normal
- Transfer switch listed FOR FIRE PUMP SERVICE specifically
5.8 Acceptance and ITM
| Test |
Requirement |
| Field acceptance flow points |
Churn, 100% rated, 150% rated |
| Acceptable performance |
>= 95% rated pressure at rated flow |
| Annual full performance test |
3 flow points, all parameters recorded |
| Weekly diesel churn |
30 min |
| Monthly electric churn |
10 min (most installations) |
5.9 Common pitfalls
Mistake 1: Mixing up 100/100 and 150/65.
Rated flow gets rated pressure; overload flow gets 65% pressure minimum.
Mistake 2: Forgetting eccentric reducer flat-side UP.
Flat side UP at the suction flange prevents air pockets that would cause cavitation.
Mistake 3: Picking horizontal split-case for suction lift.
Vertical turbine is the only listed pump type for suction lift.
6. NFPA 24 - Private Fire Service Mains
6.1 Hydrostatic testing - sec 10.10.2.2
Underground piping is hydrostatically tested at 200 psi for 2 hours. UNLIKE aboveground, NFPA 24 ALLOWS measurable leakage during the test. The maximum permissible leakage is calculated by formula in sec 10.10.2.2.6.
6.2 Flushing - sec 10.10.2.1
Required flushing velocity: 10 ft per second. Minimum flow rates by pipe size:
| Pipe size |
Min flushing flow at 10 ft/sec |
| 6 in. |
880 gpm |
| 8 in. |
1,560 gpm |
| 10 in. |
2,440 gpm |
| 12 in. |
3,520 gpm |
6.3 Cover and bury - sec 10.4.2
Minimum cover above the top of pipe in non-frost areas: 36 inches. In frost-prone regions: below the local frost line. Phoenix uses 36 in. as the standard.
OSHA cross-reference: trenches 5 ft deep or more require a protective system (Subpart P). 36 in. cover plus pipe diameter typically pushes the trench past 5 ft.
6.4 Thrust restraint - sec 10.8
Thrust blocks (concrete) or rod-and-clamp restraints required at all bends, tees, crosses, plugs, dead ends, reducers, and hydrant tees.
6.5 Pipe materials - sec 10.1
Approved: ductile iron, steel, concrete pressure pipe, copper, brass, listed plastics (PVC and HDPE). Plain unlisted cast iron is no longer accepted.
6.6 Hydrants - Chapter 7
- Spacing: approximately 250 ft typical (AHJ may require closer)
- Coverage: located so all building portions are within 250 ft of hose lay
- Outlets: typically two 2.5 in. and one 4.5 in. for engine connection
7. NFPA 25 - Inspection, Testing, and Maintenance
NFPA 25 (2023 edition) is the third heaviest subject. The single most important thing to memorize: the FREQUENCY tables.
7.1 The frequency table
| Frequency |
Items / activities |
| Weekly |
Dry/preaction/deluge gauges, diesel pump no-flow churn test (30 min), unsupervised valves |
| Monthly |
Wet pipe gauges, electric pump no-flow churn test (10 min), supervised valves |
| Quarterly |
Alarm devices, FDC, hydraulic nameplate, valve supervisory devices, main drain test (where backflow/PRV downstream), priming water, QODs |
| Semi-annual |
Dry/preaction/deluge supervisory devices |
| Annual |
Main drain test (each riser), sprinkler visual, hangers, full pump performance test, antifreeze (top + bottom), all alarms, valves cycled, deluge full trip test, low air pressure alarms, backflow performance |
| 3-year |
Internal check valves, full dry/preaction valve trip test |
| 5-year |
Internal pipe inspection, gauge replace, standpipe hydro 200/2, FDC pipe hydro 150/2, sprinkler PRV full flow, standpipe flow test |
7.2 Sprinkler sample testing
| Sprinkler type |
First test |
Subsequent |
| Standard-response (solder/old style) |
50 years |
Every 10 years |
| Quick-response (incl. ESFR/CMSA) |
20 years |
Every 10 years |
| Dry sprinklers |
10 years |
Every 10 years |
| Harsh environment |
5 years |
Every 5 years |
| Antifreeze sprinklers |
Annual concentration test (top + bottom) |
Plus standard sample testing |
Sample size: at least 4 sprinklers OR 1 percent of installed (whichever greater). If any sprinkler in the sample fails, ALL represented sprinklers must be replaced.
7.3 Tag colors - Chapter 15
| Color |
Meaning |
When used |
| Red |
IMPAIRMENT - system or component out of service |
When the system cannot perform its intended function |
| Yellow |
DEFICIENCY - functional but not code-compliant |
When the system works but a code violation exists |
| White |
INFORMATIONAL |
Records, non-required system identification |
Memory device: Red = stopped. Yellow = caution. White = info.
7.4 Owner responsibilities - Chapter 4
- Maintaining the system in operative condition
- Providing access for ITM activities
- Correcting deficiencies identified during ITM
- Managing impairments per Chapter 15
- Maintaining records (sec 4.3.1: until next ITM of same nature plus 1 year)
7.5 Main drain test - sec 13.2.5
- Annually at each system riser - default cadence
- Quarterly if a backflow preventer or PRV is installed downstream of the main control valve
7.6 Impairment program - Chapter 15
- Notify the fire department, central station, supervisory station, and insurance carrier
- Notify building occupants if alarm or sprinkler protection is impaired
- Apply a red impairment tag at the system riser
- Implement a fire watch if duration exceeds local AHJ thresholds
- Restore the system as quickly as possible
- Notify all parties when service is restored and remove the tag
Phoenix specific: notify the Phoenix Fire Alarm Room at 602-495-5555 before AND upon restoration. PFC sec 901.7.
7.7 Common pitfalls
Mistake 1: Confusing weekly and monthly pump tests.
Diesel WEEKLY 30 min. Electric MONTHLY 10 min.
Mistake 2: Forgetting 'whichever greater' on sprinkler sampling.
Min sample is 4 OR 1 percent, whichever greater.
8. IBC - International Building Code (Sprinkler Triggers)
The IBC tells you WHEN sprinklers are required. NFPA 13 tells you HOW to install them.
8.1 The sec 903.2 trigger matrix
| Group |
Sprinkler trigger |
Section |
| A-1, A-3, A-4 |
Fire area > 12,000 sq ft, OR OL >= 300, OR floor not at exit discharge |
903.2.1.1/.3/.4 |
| A-2 (food/drink/alcohol) |
Fire area > 5,000 sq ft, OR OL >= 100, OR floor not at exit discharge |
903.2.1.2 |
| A-5 (outdoor sports) |
Accessory enclosed area > 1,000 sq ft |
903.2.1.5 |
| E (educational) |
Fire area > 12,000 sq ft, OR floor not at discharge, OR daycare > 5 children > 2.5 yrs |
903.2.3 |
| F-1 (factory moderate) |
Fire area > 12,000 sq ft, > 24,000 combined, >= 3 stories |
903.2.4 |
| H (high-hazard) |
THROUGHOUT - all H occupancies |
903.2.5 |
| I (institutional) |
THROUGHOUT - all I occupancies |
903.2.6 |
| M (mercantile) |
Fire area > 12,000 sq ft, > 24,000 combined, > 3 stories |
903.2.7 |
| R (residential) |
THROUGHOUT - any R fire area, regardless of size |
903.2.8 |
| S-1 (storage moderate) |
Fire area > 12,000 sq ft, > 24,000 combined, >= 3 stories |
903.2.9 |
| S-2 (parking, enclosed) |
> 12,000 sq ft OR beneath other occupancy |
903.2.10 |
8.2 Standard reference - sec 903.3
| Standard |
Application |
| NFPA 13 (full) |
Default for all required sprinkler systems unless specifically permitted otherwise |
| NFPA 13R |
Group R occupancies up to 4 stories above grade plane AND <= 60 ft above grade plane |
| NFPA 13D |
1-2 family dwellings, townhouses, R-3 occupancies, R-4 Condition 1 |
Critical 2021/2024 IBC change: NFPA 13R height limit measured from GRADE PLANE, not podium top.
8.3 Standpipe triggers - sec 905
| Class |
Trigger |
Section |
| Class III |
Highest story floor > 30 ft above lowest FD vehicle access, OR 4+ stories above/below grade plane |
905.3.1 |
| Class I |
Non-sprinklered Group A with OL > 1,000 |
905.3.2 |
| Class II |
Per AHJ, often in stages and large performance venues |
905.3.4 |
8.4 Sprinkler supervision - sec 903.4
- All control valves controlling the water supply
- Water flow (waterflow alarm)
- Water level (where tanks are used)
- Critical air pressures (dry/preaction)
- Tamper devices on valves
8.5 Common pitfalls
Mistake 1: Mixing up A-2 (5,000) with the rest of A (12,000).
A-2 (food/drink) trigger is 5,000 sq ft fire area or OL >= 100.
Mistake 2: Forgetting that R is throughout.
Group R triggers sprinklers throughout the building with any R fire area, regardless of size.
9. OSHA - Workplace Safety for Sprinkler Trades
OSHA accounts for roughly 25 to 30 questions on a typical ASCR4 exam. Install work is construction (1926); service work in an existing building is general industry (1910).
9.1 Lockout/Tagout - 29 CFR 1910.147
The six-step procedure
- Notify affected employees that LOTO is being applied
- Shutdown using normal stopping procedures
- Isolate energy sources by operating disconnects, valves, blocks
- Apply locks and tags to each energy isolation device
- Release stored energy (springs, pressure, capacitors, suspended loads, residual heat)
- Verify isolation by attempting to start with normal operating controls; return controls to OFF
Three employee categories
| Category |
Definition |
Training |
| Authorized |
Locks/tags out machines for service or maintenance |
Full procedure including energy types, magnitudes, isolation methods |
| Affected |
Operates the machine or works in the area |
Purpose and use of procedure (NOT authorized to apply locks) |
| Other |
Employees in vicinity not in either category above |
Trained on prohibition against attempting restart |
LOTO procedures must be inspected at least annually by an authorized employee NOT using the procedure being inspected.
9.2 Confined Space - 29 CFR 1910.146
Atmospheric testing - exact sequence
- Oxygen content first (acceptable range: 19.5% to 23.5%)
- Flammable gases and vapors second (must be < 10% LEL)
- Toxic gases and vapors third
Most monitors require correct oxygen reading to accurately read other gases - that is why oxygen comes first.
Attendant duties
The attendant stays OUTSIDE the space. Continuously monitor entrants, communicate with entrants, recognize hazardous conditions and order evacuation, summon rescue. Generally does NOT enter - rescue is for trained rescue teams.
9.3 Fall Protection - 29 CFR 1926 Subpart M
| Topic |
Requirement |
Section |
| Trigger height (construction) |
6 ft above lower level |
1926.501(b)(1) |
| Trigger height (general industry) |
4 ft above lower level |
1910.28 |
| Anchor capacity |
5,000 lb per person OR 2x MAF (qualified-person designed) |
1926.502(d)(15) |
| Max arresting force on body harness |
1,800 lbf |
1926.502(d)(16) |
| Free fall limit |
6 ft maximum |
1926.502(d)(16) |
| Guardrail top rail |
42 in. plus or minus 3 in. |
1926.502(b)(1) |
| Pre-use inspection |
Before each use by user |
1926.502(d)(21) |
| Post-fall removal |
Removed from service until inspected by competent person |
1926.502(d)(19) |
9.4 Trenching/Excavation - 29 CFR 1926 Subpart P
| Topic |
Requirement |
Section |
| Protective system trigger |
5 ft depth or more (any depth if cave-in risk; stable rock exempt) |
1926.652(a)(1) |
| Means of egress trigger |
4 ft depth or more - ladder/ramp within 25 ft lateral travel of any worker |
1926.651(c)(2) |
| Daily inspection |
By a competent person, before each shift, after rainstorms |
1926.651(k) |
| Soil typing |
By competent person using Appendix A visual and manual tests |
App A |
| Spoil and equipment setback |
>= 2 ft from edge |
1926.651(j) |
Soil types and slope ratios
| Soil type |
Description |
Max slope (H:V) |
| Stable rock |
Solid mineral matter that can be excavated with vertical sides |
Vertical |
| Type A |
Cohesive, unconfined comp strength >= 1.5 tsf (clay, silty clay) |
0.75:1 (53 deg) |
| Type B |
Cohesive 0.5-1.5 tsf, granular cohesionless (silt, sandy loam) |
1:1 (45 deg) |
| Type C |
Cohesive < 0.5 tsf, gravel, sand, submerged soils |
1.5:1 (34 deg) |
| Topic |
Requirement |
| SDS access |
Readily accessible to employees during each work shift |
| SDS format |
16 sections, GHS-aligned |
| Workplace label |
Product ID + signal word + pictograms + hazard statement + precautionary statement |
| Sprinkler-trade chemicals requiring SDS |
Solvent cement, primer, antifreeze, thread sealants, lubricants |
9.6 Hot Work
- Hot work permit issued by a designated permit-authorizing individual
- Removal or shielding of combustibles within 35 ft of the work
- Fire watch DURING the work and for 30 minutes AFTER
- Approved fire extinguisher on hand
9.7 Common pitfalls
Mistake 1: Confusing 4 ft (general industry) with 6 ft (construction).
Sprinkler INSTALLATION is construction (Subpart M, 6 ft trigger).
Mistake 2: Forgetting the order of atmospheric tests.
Always: Oxygen, Flammables, Toxics. In that order.
Mistake 3: Mixing 4 ft (egress) and 5 ft (protective system) for trenches.
4 ft = ladder/ramp required. 5 ft = protective system. Both can apply to the same trench.
Mistake 4: Forgetting the 30-minute fire watch AFTER hot work.
Fire watch required DURING and for 30 MINUTES AFTER work ceases.
10. CPVC - BlazeMaster and Manufacturer Rules
CPVC is governed primarily by manufacturer's installation instructions (BlazeMaster Tech Handbook, Tyco/Flameguard, etc.) - NOT by NFPA.
10.1 Pressure and temperature ratings
CPVC fire sprinkler pipe is rated 175 psi at temperatures up to 150 deg F. CPVC is permitted only in WET PIPE systems unless specifically listed for an exception.
10.2 Hanger spacing
| Pipe size |
Maximum hanger spacing |
| 3/4 in. |
5 ft 6 in. |
| 1 in. |
6 ft |
| 1.25 in. |
6 ft 6 in. |
| 1.5 in. |
7 ft |
| 2 in. |
8 ft |
| 2.5 in. |
9 ft |
| 3 in. |
10 ft |
Hangers must also be installed within 12 in. of each elbow or tee.
10.3 The compatibility rules
Antifreeze - permitted
USP-grade glycerin only. Factory-mixed. UL 2901 listed.
Antifreeze - prohibited
All glycols (ethylene glycol, propylene glycol). All brines. These attack CPVC and cause stress-cracking failures.
Thread sealant
PTFE thread tape (Teflon tape) ONLY. NO oil-based pipe dope, NO paste sealants, NO solvent caulks.
10.4 Joint preparation - proper sequence
- Cut the pipe square using a wheel cutter or fine-tooth saw
- Deburr the inside; chamfer/bevel the outside
- Dry-fit to verify proper engagement
- Apply primer (where required by code/manufacturer)
- Apply solvent cement to both pipe and fitting
- Assemble with a quarter-turn rotation as you push together
- Hold for the listed set time
10.5 Set time vs cure time
SET time is how long before you can move the joint. CURE time is how long before you can pressurize and test. They are NOT the same.
| Pipe size |
Set time at 60-100 deg F |
Set time below 40 deg F |
| 1/2 in. to 1.25 in. |
~1 minute |
~5 minutes |
| 1.5 in. to 2 in. |
~3 minutes |
~10 minutes |
| 2.5 in. to 3 in. |
~5 minutes |
~15 minutes |
10.6 Concealment rules
- Behind 3/8 in. gypsum
- Behind 1/2 in. plywood
- Behind a listed lay-in panel ceiling
EXPOSED installation is permitted ONLY when the specific sprinkler-and-pipe combination is listed for exposed installation under the actual ceiling type.
10.7 Common pitfalls
Mistake 1: Using oil-based pipe dope on a threaded transition.
PTFE tape ONLY on CPVC.
Mistake 2: Using glycol antifreeze with CPVC.
USP glycerin only. Glycol attacks CPVC.
Mistake 3: Pressurizing before cure time.
Use the manufacturer's cure time table.
11. Hydraulics - The Math Behind the Code
11.1 The fundamental discharge equation
Q = K x sqrt(P) where Q is flow in gpm, P is pressure in psi at the sprinkler, and K is the K-factor
- To find K from a tested sprinkler: K = Q / sqrt(P)
- To find required pressure for a target flow: P = (Q / K)^2
Worked examples
Example 1 - K-5.6 sprinkler at 7 psi minimum: Q = 5.6 x sqrt(7) = 5.6 x 2.646 = 14.8 gpm. Approximately 15 gpm.
Example 2 - K-8.0 sprinkler must flow 28 gpm. Required pressure: P = (28 / 8.0)^2 = 3.5^2 = 12.25 psi.
Example 3 - Sprinkler tested at 50 psi flows 39.6 gpm. K = 39.6 / sqrt(50) = 39.6 / 7.07 = 5.6.
11.2 Common K-factors
| K-factor |
Typical use |
| K-5.6 |
Most common Light/Ordinary Hazard - the floor for NFPA 13 commercial |
| K-8.0 |
Higher-flow density designs, light storage |
| K-11.2 |
Storage applications |
| K-14, K-16.8, K-22.4, K-25.2, K-28.0 |
ESFR / CMSA / large-drop storage |
11.3 Conversions and constants
| Conversion |
Value |
| Pressure to head |
1 psi = 2.31 ft of water column |
| Head to pressure |
1 ft of water = 0.433 psi |
| Cubic foot to gallon |
1 cubic ft = 7.48 gallons |
| Water weight |
1 cubic ft of water = 62.4 lb at 60 deg F |
| Gallon weight |
1 gallon = 8.33 lb |
| Atmospheric pressure |
14.7 psi at sea level |
11.4 Hazen-Williams C-factors
| Pipe material / condition |
C-factor |
| Dry steel (corroded interior) |
100 |
| Wet steel |
120 |
| Cement-lined cast or ductile iron |
140 |
| Copper, plastic (CPVC) |
150 |
Friction loss varies with flow raised to approximately the 1.85 power. Doubling the flow increases friction loss roughly 3.6x.
11.5 Components of total hydraulic demand
- Sprinkler operating pressure at the most-remote sprinkler (typically 7 psi minimum)
- Friction loss through all piping from supply to the most-remote sprinkler
- Elevation pressure (0.433 psi per foot of vertical rise)
All three sum to give the demand at the base of riser. Hose stream allowance is added separately at the supply connection.
11.6 Common pitfalls
Mistake 1: Squaring the wrong way.
Q = K x sqrt(P) - the square root is on PRESSURE, not flow.
Mistake 2: Adding hose stream at the wrong location.
Hose stream allowance is added at the supply connection.
Mistake 3: Confusing 0.433 and 2.31.
0.433 psi per foot. 2.31 feet per psi. They are reciprocals.
12. Phoenix / AHJ - Field Operations Context
This chapter is REFERENCE for Phoenix metro field work. The CSA ASCR4 exam itself does not test Phoenix-specific code. However, Phoenix specifics drive every job once the credential is held.
12.1 The Phoenix Fire Code
The Phoenix Fire Code (PFC) is the 2024 International Fire Code as amended by Phoenix City Ordinances:
- Ord. G-7242 (effective 5/4/2024) - added the current Phoenix amendments
- Ord. G-7397 (effective 8/1/2025) - moved the base code to the 2024 IFC
12.2 The Business Certificate - PFC sec 105.8
- 3-year term
- $150 per system type
- Arizona ROC contractor license required
- Arizona TPT registration required
- Designated 'competent party' on file with PFD
Competent party credentials - sec 105.8.1
- CSA Level 2 or higher in the applicable category (ASCR4 satisfies this)
- NICET Levels 1 through 4 in the applicable category
- Arizona-registered Professional Engineer
- Factory-trained certification (NFPA 72 fire alarm only)
12.3 The Bret Tarver Sprinkler Ordinance
Phoenix's amendment to IBC sec 903 - named for firefighter Bret Tarver who lost his life at the Southwest Supermarket fire in 2001. Sprinklers are required throughout new construction in:
- All Group A, B, E, F, H, I, M, R-1, R-2, R-4, and S occupancies of any size
- All R-3 occupancies including IRC 1- and 2-family dwellings
- All Group U occupancies exceeding 5,000 sq ft
12.4 Annual ITM reporting - The Compliance Engine
| Item |
Detail |
| Reporting platform |
TCE - tce.mybrycer.com |
| Vendor |
Brycer |
| Contractor support |
tce@mybrycer.com or 630-413-9511 |
| What gets reported |
Sprinkler ITM, fire alarm ITM, fire pump ITM, kitchen suppression |
| Deficiency routing |
Automatic to PFD ITM Section after upload |
12.5 Impairment notification
Phoenix Fire Alarm Room: 602-495-5555 - this is the number every tech needs memorized.
This is NOT 911. Use 911 only if there is an active emergency. Use 602-495-5555 for impairment notifications, system out-of-service notifications, and system restoration.
12.6 Plan submittal requirements
- Site plan scale: 1 in. = 50 ft
- Fire protection plan scale: 1/8 in. = 1 ft
- Bar graph scale required on every page
- Directional arrow (north arrow) required on every page
- Fire flow test data must be witnessed by AHJ within recency window (typically 12 months)
12.7 Field operations workflow - Phoenix specific
- Hold ASCR4 (CSA) - personal credential
- Company holds Phoenix Business Certificate (PFC sec 105.8) with you as competent party
- Annual ITM completed per NFPA 25
- Report uploaded to TCE within the AHJ window after the visit
- Deficiencies tracked through TCE; impairments notified to 602-495-5555
Appendix A. Quick Reference Cards
A.1 NFPA 13 - The Big Numbers
| Topic |
Number |
| Standard pendent/upright deflector below ceiling (unobstructed) |
1 in. min, 12 in. max |
| Standard sidewall deflector below ceiling |
4 in. to 6 in. |
| Min spacing between sprinklers (no baffle) |
6 ft on center |
| Max spacing - Light/Ordinary Hazard |
15 ft |
| Max spacing - Extra Hazard density >= 0.25 |
12 ft |
| Light Hazard max coverage (hydraulic) |
225 sq ft |
| Ordinary Hazard max coverage |
130 sq ft |
| Storage clearance to top - standard spray |
18 in. |
| Storage clearance to top - ESFR |
36 in. |
| Min sprinkler operating pressure |
7 psi |
| Max sprinkler operating pressure |
175 psi |
| Aboveground hydrostatic test |
200 psi for 2 hours |
| Dry/preaction air leak test |
40 psi for 24 hr, max 1.5 psi loss |
| 3x Rule max |
3x obstruction width, max 24 in. |
| 4x Rule (extended-coverage) max |
4x obstruction width, max 36 in. |
| Lateral sway brace spacing |
40 ft on center |
| Longitudinal sway brace spacing |
80 ft on center |
A.2 NFPA 13 - Density / Area / Hose Stream
| Hazard |
Density |
Design Area |
Hose Stream |
Duration |
| Light |
0.10 gpm/sq ft |
1500 sq ft |
100 gpm |
30 min |
| Ordinary 1 |
0.15 |
1500 |
250 |
60-90 min |
| Ordinary 2 |
0.20 |
1500 |
250 |
60-90 min |
| Extra 1 |
0.30 |
2500 |
500 |
90 min |
| Extra 2 |
0.40 |
2500 |
500 |
120 min |
A.3 NFPA 13D vs 13R
| Topic |
13D |
13R |
| Scope |
1-2 family, manufactured, townhouse |
Residential <=4 stories AND <=60 ft above grade plane |
| Water duration |
10 min (7 if 1-story <=2,000 sq ft) |
30 min |
| Max design sprinklers |
2 |
Up to 4 |
| Bathroom omit |
<= 55 sq ft |
<= 55 sq ft |
| Closet omit |
<= 24 sq ft, dim <= 3 ft |
<= 24 sq ft, dim <= 3 ft |
| Egress corridor |
N/A |
REQUIRED to be sprinklered |
| Multipurpose system |
Permitted |
N/A |
A.4 NFPA 14 Standpipes
| Class |
Outlet |
Min Residual |
Min Flow |
| I |
2.5 in. |
100 psi |
500 + 250 each, cap 1000-1250 |
| II |
1.5 in. |
65 psi |
100 gpm fixed |
| III |
Both |
100 / 65 psi |
Same as Class I |
Max static at any hose connection: 175 psi. Hose connection height: 3-5 ft above floor. Hydrostatic test: 200 psi for 2 hours. 2024 NEW: dry standpipes air-supervised at 7-20 psi.
A.5 NFPA 20 Fire Pumps
| Item |
Spec |
| Performance: 100% flow |
100% rated pressure |
| Performance: 150% flow |
>=65% rated pressure |
| Performance: churn (no flow) |
<=140% rated pressure |
| Pump room minimum temp |
40 deg F |
| Suction velocity at 150% flow |
<=15 ft/sec |
| Discharge velocity at 150% flow |
<=20 ft/sec |
| Eccentric reducer at suction |
Flat side UP |
| Suction lift - only listed type |
Vertical turbine |
| Diesel fuel tank |
1 gal/HP + 5% expansion + 5% sump |
| Diesel batteries |
2, each independently capable |
| Diesel cranking cycles |
6 cycles, 15 sec on / 15 sec off |
| Jockey pump capacity |
Make up leakage in 10 min, min 1 gpm |
| Acceptable performance |
>=95% rated pressure at rated flow |
A.6 NFPA 25 ITM Frequency
| Frequency |
Items |
| Weekly |
Dry/preaction/deluge gauges; diesel pump churn (30 min) |
| Monthly |
Wet pipe gauges; electric pump churn (10 min) |
| Quarterly |
Alarm devices; FDC; main drain (when backflow/PRV downstream) |
| Annual |
Main drain each riser; full pump performance; antifreeze top+bottom; deluge full trip |
| 3-year |
Full dry/preaction trip test; internal check valves |
| 5-year |
Internal pipe inspection; gauge replace; FDC pipe hydro 150/2; standpipe flow test |
Sprinkler sample test: Standard 50/10, QR 20/10, Dry 10/10, Harsh 5/5. Sample: 4 OR 1% (whichever greater). Tags: Red impairment, Yellow deficiency, White info.
A.7 IBC Sprinkler Triggers
| Group |
Trigger |
| A-1, A-3, A-4 |
>12,000 sq ft OR OL >=300 |
| A-2 (food/drink) |
>5,000 sq ft OR OL >=100 |
| E |
>12,000 sq ft OR daycare >5 children >2.5 yrs |
| F-1 |
>12,000 sq ft, >24,000 combined, >=3 stories |
| H |
THROUGHOUT all H |
| I |
THROUGHOUT all I |
| M |
>12,000 sq ft, >24,000 combined, >3 stories |
| R |
THROUGHOUT - any R fire area |
| S-1 |
>12,000 sq ft, >24,000 combined, >=3 stories |
A.8 OSHA Quick Reference
| Topic |
Number |
| Fall trigger - construction |
6 ft |
| Fall trigger - general industry |
4 ft |
| Fall arrest anchor capacity |
5,000 lb per person OR 2x MAF |
| Max arresting force on body harness |
1,800 lbf |
| Free fall limit |
6 ft |
| Guardrail top rail |
42 in. plus or minus 3 in. |
| Trench protective system trigger |
5 ft (or any depth if cave-in risk) |
| Trench egress trigger |
4 ft, ladder/ramp within 25 ft |
| Confined space O2 acceptable |
19.5% to 23.5% |
| Confined space test order |
1) Oxygen, 2) Flammables, 3) Toxics |
| LOTO 6 steps |
Notify, Shutdown, Isolate, Lock/Tag, Release stored, Verify |
| Hot work clearance from combustibles |
35 ft |
| Hot work fire watch after work |
30 minutes |
A.9 Phoenix / AHJ
| Item |
Detail |
| Phoenix Fire Alarm Room |
602-495-5555 |
| TCE / Brycer support |
tce@mybrycer.com or 630-413-9511 |
| Bret Tarver - throughout |
All A, B, E, F, H, I, M, R-1, R-2, R-4, S any size; all R-3; U >5,000 sq ft |
| Business Cert |
PFC sec 105.8 - 3-yr, $150/system |
| Plan submittal scale - site |
1 in. = 50 ft |
| Plan submittal scale - fire protection |
1/8 in. = 1 ft |
B.1 Sprinkler discharge
Q = K x sqrt(P)
Q = flow in gpm. P = pressure in psi at the sprinkler. K = sprinkler K-factor.
Rearrangements: K = Q / sqrt(P). P = (Q / K)^2.
B.2 Pressure / head
1 psi = 2.31 ft of water column
1 ft of water = 0.433 psi
These are reciprocals (1/0.433 = 2.31).
B.3 Volume / weight
- 1 cubic foot = 7.48 gallons
- 1 cubic foot of water at 60 deg F = 62.4 lb
- 1 gallon of water = 8.33 lb
- Atmospheric pressure at sea level = 14.7 psi (1 atm)
B.4 Hazen-Williams C-factors
| Pipe material |
C-factor |
| Dry steel |
100 |
| Wet steel |
120 |
| Cement-lined cast/ductile iron |
140 |
| Copper, plastic (CPVC) |
150 |
B.5 Worked examples - drill these
Example 1 - K-5.6 at minimum pressure
Q = 5.6 x sqrt(7) = 5.6 x 2.646 = 14.8 gpm
Example 2 - K-8.0 needs 32 gpm
P = (32 / 8.0)^2 = 4^2 = 16 psi
Example 3 - 50 ft elevation pressure
50 ft x 0.433 psi/ft = 21.65 psi
Example 4 - K verification
Sprinkler at 25 psi flowing 28 gpm. K = 28 / sqrt(25) = 28 / 5 = 5.6.
Example 5 - Flushing flow at 10 ft/sec
6 in. underground main: 880 gpm. (8 in. = 1,560; 10 in. = 2,440; 12 in. = 3,520.)
Appendix C. Pre-Tab Strategy for Open-Book Exam
Pre-test checklist. The night before the exam, sit down with each code book and tab the sections listed below using permanent tabs (Avery, Post-It DURABLE). Do NOT use removable Post-Its - exam rules forbid them.
C.1 NFPA 13 - tab targets
- Ch. 4 - General Requirements
- Ch. 6 - Classification of Commodities
- Ch. 7 - Sprinkler temp ratings (Table 7.2.4.1)
- Ch. 8 - Min/max operating pressure
- Ch. 10 - Sprinkler Position (THE chapter)
- Ch. 16 - System Components
- Ch. 17 - Hanging
- Ch. 18 - Bracing
- Ch. 19 - Design Approaches
- Ch. 23 - ESFR Sprinklers
- Ch. 27 - Plans and Calculations
- Ch. 29 - System Acceptance
C.2 NFPA 13D - tab targets
- Ch. 1 - Scope
- Ch. 6 - Water Supply (10 min, 7 min)
- Ch. 7 - Pipe and Fittings
- Ch. 8 - System Design
C.3 NFPA 13R - tab targets
- Ch. 1 - Scope (4 stories AND 60 ft)
- Ch. 6 - System Design
- Ch. 10 - Local Alarm requirement
C.4 NFPA 14 - tab targets
- Ch. 3 - Definitions
- Ch. 6 - System Components (2024 air supervision)
- Ch. 7 - Installation Requirements
- Ch. 11 - Acceptance Testing
C.5 NFPA 20 - tab targets
- Ch. 4 - General Requirements
- Ch. 7 - Vertical Shaft Turbine
- Ch. 9 - Electric Drive
- Ch. 10 - Electric Drive Controllers
- Ch. 11 - Diesel Engine Drive
- Ch. 12 - Diesel Engine Controllers
- Ch. 14 - Field Acceptance Test
C.6 NFPA 24 - tab targets
- Ch. 7 - Hydrants
- Ch. 10 - Installation Requirements
C.7 NFPA 25 - tab targets
- Ch. 4 - Owner's Responsibility
- Ch. 5 - Sprinkler Systems
- Ch. 6 - Standpipe and Hose Systems
- Ch. 8 - Pumps
- Ch. 13 - Common Components and Valves
- Ch. 14 - Internal Piping Inspection
- Ch. 15 - Impairments
C.8 IBC - tab targets
- Ch. 3 - Use and Occupancy Classification
- Ch. 5 - Tables 504/506
- Ch. 9 - sec 903 (sprinkler triggers)
- Ch. 9 - sec 905 (standpipes)
- Ch. 9 - sec 913 (fire pumps)
- Ch. 10 - Table 1004.5 (occupant load)
C.9 OSHA - tab targets
- 1910.146 - Confined Spaces
- 1910.147 - LOTO
- 1910.252 - Welding/Hot Work
- 1910.1200 - HazCom
- 1926.501-502 - Fall Protection
- 1926.651-652 - Excavation
- 1926 Subpart P, App A and B - soil typing
C.10 Final test-day reminders
Eat before you go in. The exam is 3 hours. Bring water if allowed. Get there 20 minutes early to avoid stress.
First pass: answer everything you know cold. Skip the rest. Don't get stuck on one question.
Second pass: use your books for the flagged questions. Each question should take under 3 minutes including book lookup.
Third pass: review flagged answers and skim your initial answers. Don't second-guess unless you have a specific reason.
Members First. G$D. True North. You are going to crush this.